RFQ Response: Supply of Hydraulic Hose Assemblies to Caterpillar Thailand
RFQ Response: Supply of Hydraulic Hose Assemblies to Caterpillar Thailand
Evahan provided a quotation and proposal for the supply of over 3,000 hydraulic hose assembly SKUs to Caterpillar Thailand's underground mining and bulldozer OEM plants in Rayong
Posted
120,000 Hydraulic Hose Assemblies per Annum Supplied to Caterpillar Thailand
Evahan prepared a RFQ Response for Delta Hydraulics Thailand Ltd to continue the supply approximately 120,000 hose assemblies per annum to the two Caterpillar plants in Rayong Thailand. At these plants Cat manufacture all D5, D6, D7 and D8 bulldozers sold outside of the USA, and in the second plant their range of hard rock underground mining wheel loaders and dump trucks.
There were many challenges with preparing this Request for Quotation Response:
120,000 per annum hose assemblies spread over approximately 3,000 SKUs
Many low volume SKUs for machines specified with Caterpillar's end-customer "option-fit"
True JIT basis. The Caterpillar plants would hold the hydraulic hoses no longer than 48 hours (excluding weekends or public holidays) before they were fitted to a bulldozer or hard rock underground mining vehicle
POU delivery complexities, requiring sophisticated customised job ticketing and delivery modules in the cloud-based ERP system
100% open-book component supply costs and terms from Caterpillar preferred suppliers in USA, China, Italy, Japan and Australia
Agreed base foreign Exhange cross rates between USD, THB, EUR, JPY and AUD, with risk sharing mechanisms for 10% +/- variance from the agreed base
Integration with Caterpillar's demand-pull signal system, called their MRC
FIRM status demand conformation for hose assemblies up to 12 weeks after the components for those hose assemblies were already ordered
Significance variance in shipping times of components from China vs USA vs Italy
EDI integration with Caterpillar's Advanced Shipping Notification (ASN) and Accounts Payable invoicing system
60-day payment terms
Constant engineering change notifications (ECNs) particularly on newer machine models
Last minute demand signal changes caused by the Caterpillar re-ordering production schedules
Unique Thailand taxation compliance regulations related to the need to produce hard-copy invoices in triplicate for example.
Significant administration costs associated with compliance to Delta Thailand's and Caterpillar's Thailand Bord of Investment compliance to access custom tariffs incentives and permission for foreign owned corporations to operate in the country.
Presenting the open book component cost & pricing element of the 3,000 SKUs quoted in a format prescribed by Caterpillar, that no off-the-shelf ERP or quote system could do
Delta is absorbing significant freight increases overcoming the shipping and airfreight difficulties and cost increases resulting from the Covid 19 and terrorist activity in the Red Sea
Evahan is assisting Delta with data analysis and negotiation associated with the significant freight increases it has incurred overcoming the shipping and airfreight difficulties and cost increases resulting from Covid 19 and terrorist activity in the Red Sea
Delta's customer Caterpillar decreased inventory, increased manufacturing velocity and developed a faithful and nimble supplier, literally "across-the-road" that could respond to last minute demand signal changes and engineering change request notifications
Do you require an experienced consultant to assist you prepare or refine a RFP or RFQ Response.? Contact Evahan Managing Director and Principal Consultant Jason Bresnahan to explore how we can support you.
Evahan consultants are experienced in preparing sophisticated RFP Responses for all levels of government and large multi-national corporations.